Description
-
Precise removal of previous drainage system
-
Placement of two storm inlets
-
20' deep 2x4 inlet​
-
3' deep 2x4 inlet
-
-
Implementation of proper drainage system through the use of 76' of piping
-
40' of 24" HDPE​ pipe
-
36' of 12" HDPE pipe
-
-
Seamless connection of the drainage system to an 18" storm pipe
-
Hillside stabilization using 450 tons of Rip Rap reinforcing rock and stabilization fabric
-
Repaving and landscaping to return the job site to previous condition
-
Timely completion of the project within 30 days